Skip to the content.

FINAL REBAR DESIGN - SOUTH ABUTMENT

Based on Your STEP File (Abutment-South.step)


βœ… PERFECT FIT - YOU HAVE ENOUGH REBAR!

Your inventory: 40 bars Γ— 10 feet = 400 linear feet
Required for this abutment: 138 linear feet (14 bars)
βœ“ SURPLUS: 262 feet (26 extra bars for the north abutment or other uses!)


πŸ“ YOUR ABUTMENT SPECIFICATIONS (From STEP File)

Dimensions

Structure Breakdown

This is a REALISTIC, BUILDABLE Design! 🎯

This is exactly the right size for:


πŸ”¨ COMPLETE REBAR SCHEDULE

Summary Table

Mark Description Qty Length Each Total Length # of 10’ Bars
R1 Base Longitudinal 2 9.0’ 18.0’ 2 bars
R2 Base Transverse 8 3.0’ 24.0’ 3 bars
R3 Wall Vertical (Front) 8 3.0’ 24.0’ 3 bars
R4 Wall Vertical (Back) 8 3.0’ 24.0’ 3 bars
R5 Wall Horizontal Ties 16 3.0’ 48.0’ 5 bars
Β  Β  Β  TOTAL: 138 feet 14 bars

You need only 14 of your 40 bars for this abutment!


πŸ“‹ DETAILED CUTTING & BENDING INSTRUCTIONS

BAR TYPE R1: Base Longitudinal (2 bars)

Purpose: Run along the 2-foot depth, supporting base slab

Cutting:

Bending:

Before:  |-----------------------------------|
         |<---------- 9'-0" ----------->|

After:      |--------------------------|
         ↑  |<------- 8'-0" ------->| ↑
         6"                           6"
         hook                        hook

Installation:


BAR TYPE R2: Base Transverse (8 bars)

Purpose: Run across the 8-foot length, forming base grid

Cutting:

Bending:

Before:  |----------|
         |<- 3'-0" ->|

After:      |------|
         ↑  |<2'>| ↑
         6"        6"

Installation:


BAR TYPE R3: Wall Vertical - Front Face (8 bars)

Purpose: Vertical reinforcement on front (approach) side

Cutting:

Bending:

Before:  |----------|
         |<- 3'-0" ->|

After:       |------ 6" hook
             |
            30" vertical
             |
          6" lap into base

Installation:


BAR TYPE R4: Wall Vertical - Back Face (8 bars)

Specifications: IDENTICAL to R3

Cutting: Same as R3 Bending: Same as R3 Installation: Same as R3, but on back (creek) side

Cutting from: 3 more of your 10’ bars


BAR TYPE R5: Wall Horizontal Ties (16 bars)

Purpose: Horizontal reinforcement connecting front and back faces

Cutting:

Bending:

Before:  |----------|
         |<- 3'-0" ->|

After:     |--------|
         ↓ |<-24"->| ↓
         6"          6"
        hook        hook

Installation:


🎯 MATERIAL SUMMARY

Rebar (#4 Grade 60)

| Item | Quantity | Cost Estimate | |β€”β€”|β€”β€”β€”-|β€”β€”β€”β€”β€”| | Bars needed | 14 bars @ 10’ | ~$112 | | YOU HAVE | 40 bars @ 10’ | Already paid | | Surplus | 26 bars | Can use for north abutment! |

Concrete

AB3 Aggregate Base

Steel Bearing Plates

Ground Anchors

Drainage

Accessories


πŸ’° TOTAL PROJECT COST

Item Cost
Rebar (you have it!) $0
Concrete (2 CY) $300
AB3 Base $30
Bearing Plates (2) $200
Ground Anchors (6) $240
Drainage Pipes $40
Forms & Accessories $150
TOTAL MATERIALS $960

Plus labor if hiring: $500-800

TOTAL PROJECT: $1,000-1,800


πŸ”§ CONSTRUCTION SEQUENCE

Week 1: Site Preparation

Day 1-2: Excavation

Day 3: AB3 Base

Day 4: Ground Anchors


Week 2: Base Slab

Day 5: Base Rebar & Setup

Day 6: Base Pour

Day 7-13: Cure Base


Week 3: Wall Construction

Day 14: Wall Rebar

Day 15: Wall Forms

Day 16: Wall Pour

Day 17-23: Cure Wall


Week 4: Finishing

Day 24: Form Removal

Day 25-26: Backfill

Day 27: Drainage

Day 28: Final Cure & Inspection


βœ… INSPECTION CHECKLIST

Pre-Pour Inspection (Base)

Pre-Pour Inspection (Wall)

During Pour

Final Inspection


πŸ“Š STRUCTURAL CAPACITY

Design Loads

Dead Load (per bearing plate):

Live Load:

Total Design Load: ~6,000 lbs per abutment

Safety Factors

ALL SAFETY FACTORS EXCEED CODE REQUIREMENTS βœ“

This abutment is over-designed for a John Deere 2025R, giving excellent safety margin!


πŸŽ“ KEY CONSTRUCTION TIPS

Rebar Installation

  1. Use proper chairs: Concrete chairs maintain 3” cover - don’t use wood blocks!
  2. Tie everything: Wire-tie all rebar intersections - prevents movement during pour
  3. Check cover twice: Measure cover before and after tying - #1 inspection failure
  4. Clean rebar: Remove loose rust, mud, oil - affects bond strength

Concrete Placement

  1. Order extra: Get 2.0 CY even though you need 1.78 - allows for waste/spillage
  2. Vibrate properly: Insert vibrator every 18-24” - eliminates air pockets
  3. Don’t overwork: Stop vibrating when large air bubbles stop rising
  4. Weather matters:
    • Ideal: 50-80Β°F
    • Hot weather (>85Β°F): Wet curing essential, may need evaporation retarder
    • Cold weather (<40Β°F): Protect from freezing, extend cure time

Critical Mistakes to Avoid

  1. ❌ Insufficient AB3 compaction β†’ Settlement β†’ Catastrophic failure
  2. ❌ Poor concrete cover β†’ Rust β†’ Structural weakness in 5-10 years
  3. ❌ Bearing plates misaligned β†’ Eccentric loading β†’ Cracking
  4. ❌ Premature loading β†’ Cracking β†’ Reduced strength
  5. ❌ Inadequate vibration β†’ Honeycombing β†’ Weak structure

πŸ“ž WHEN TO CALL A PROFESSIONAL

You Should Hire an Engineer If:

You Can DIY If:


🎯 NEXT STEPS - DECISION POINT

Before I Generate More Files, Please Confirm:

1. Dimensions Correct?

2. This is for ONE abutment only?

3. What files do you want me to generate?

4. Any modifications needed?


βœ… SUMMARY - YOU’RE READY TO BUILD!

Your situation:

This is a MUCH better project than the 36’ wide version we looked at earlier!

Please confirm the dimensions and let me know what additional files you’d like me to generate. Once you approve, I’ll create all the final deliverables.


Document Date: November 2025
Status: AWAITING YOUR CONFIRMATION
Based On: Abutment-South.step (verified dimensions)
Design By: Structural analysis optimized for your inventory

Ready to proceed? πŸš€